The Delhi Metro Rail Corporation Ltd. (DMRC) has issued Letter of Acceptance (LOA) to M/s Aarvanss Buildwell and Infracon LLP for Design, Supply, Erection, Testing & Commissioning for Modification and Raising the Height of Existing 220kV Double Circuit and 110kV/22kV Multi Circuit Transmission Line of Tata Power at Milind Nagar, crossing the proposed Metro Corridor (near Saki Vihar Metro Station) from Swami Samarth Nagar to Vikhroli (EEH) of Mumbai Metro at the total cost of INR 26.99 Crore.
- Tender Ref No: DMRC-MU-LINE6-BEUD-01
- Name of work: Contract DMRC-MU-LINE6-BEUD-01: Design, Supply, Erection, Testing & Commissioning for Modification and Raising the Height of Existing220kV Double Circuit and 110kV/22kV Multi Circuit Transmission Line of Tata Power at Milind Nagar, crossing the proposed Metro Corridor (near Saki Vihar Metro Station) from Swami Samarth Nagar to Vikhroli (EEH) of Mumbai Metro.
- The work shall be completed within 12 Months.
In July Last year, the DMRC had invited online open e-tenders for the Contract: DMRC-MU-LINE6-BEUD-01.
Mumbai Metro Line-6 Project update:
Updates as on 01th Nov 2020.
Sr. No. | Name of Work | Status |
1 | Soil Investigation Works | 85.82% completed. |
2 | Utility Works | 59.95% completed. |
3 | Piling Works | 48.36% completed. |
4 | Pile Cap Works | 34.32% completed. |
5 | Pier Works | 24.42% completed. |
6 | Station Work | 15.82% completed. |
Source: DMRC-Tender Update | Image Credit (representational): MMRDA