Aquarian Enterprises bags Rs. 31.6 crore order for electrical works for Delhi-Gurugram-SNB RRTS Corridor

The National Capital Region Transport Corporation Limited has issued a Letter of Acceptance (LOA) to M/s Aquarian Enterprises for Shifting/Modification work of 66KV/132KV EHV lines of HVPNL infringing Delhi-Gurugram-SNB RRTS Corridor.

  • Tender No.: DA/UD/COR-OF/024
  • Name of work: DA/UD/COR-OF/024 – Shifting/Modification work of 66KV/132KV EHV lines of HVPNL infringing Delhi-Gurugram-SNB RRTS Corridor.
  • Awarded Value: Rs 31.64 Crore
  • Completion Period: 9 Months

Nos. of tenders received:

  • M/s Rahul Agencies
  • M/s Gayatri Ganga Construction
  • Joint Venture of M/s PSH Techno Engg. Pvt. Ltd. and M/s L S Cable (I) Pvt. Ltd.
  • M/s Bajaj Electricals Limited
  • M/s Aquarian Enterprises

Nos. and names of parties qualified after technical evaluation:

  • M/s Bajaj Electricals Limited
  • M/s Aquarian Enterprises

Nos. and names of parties not qualified after technical evaluation:

  • M/s RAHUL AGENCIES
  • M/s Gayatri Ganga Construction
  • Joint Venture of M/s PSH Techno Engg. Pvt. Ltd. and M/s L S Cable (I) Pvt. Ltd.

Contract Awarded To: 

  • M/s Aquarian Enterprises

Project Description:

This corridor Delhi (SKK)-SNB RRTS Corridor originates from Sarai Kale Khan in Delhi and ends at SNB in Rajasthan. Key salient features are as follows:

  • Route length: 106.5 Km.
  • States covered: 3 (Delhi, Haryana, Rajasthan).
  • Length of corridor by state: 82.49 km (Haryana), 22.08 km (Delhi) and 1.93 km (Rajasthan).
  • Number of stations: 16.
  • Elevated/Underground sections: While almost the entire route length in Delhi is Underground, the route length in Haryana is mostly elevated except 14.08 Km. underground. The route length in Rajasthan is completely elevated. Elevated portion of the RRTS corridor in Haryana state has been planned along the median/left/right of old Delhi-Gurugram road, Sector-17 road in Gurugram area and along NH-48 up to SNB (Rajasthan State Border). In this corridor one maintenance depot at Dharuhera (at grade) and a stabling facility at Manesar have been planned.

Additional Details:

  • One of the three RRTS corridors prioritized for implementation, Delhi-Gurugram-Alwar is planned to be implemented in three stages. 
  • In stage I, Delhi-Gurugram-Rewari-SNB Urban Complex will be constructed. 
  • In Stage II, it will  be extended  from  SNB Urban Complex to Sotanala and in Stage III, SNB Urban Complex to Alwar will be constructed. 
  • The 106 km long Delhi-Gurugram-SNB corridor will be elevated for about 71 km (11 stations), the remaining 35 km (5 stations) will be constructed underground, mostly in Delhi & Gurugram. 
  • This corridor will converge with other RRTS corridors in Sarai Kale Khan and will be interoperable, facilitating commuters’ movement from one corridor to another without the hassle of changing trains.
  • Once constructed, the corridor is expected to bring down the travel time between SKK-SNB in less than70 minutes (106 km). 
  • The daily ridership on this corridor is estimated to be 8.5 Lakhs in 2025.

Source: NCRTC-Tender Update | Image Credit (representational): NCRTC