Chennai Metro Tender Update: M/s. Linxon India Private Limited bags contract for supply of SCADA, OHE & Switching Stations for Corridor 3 & 5 of Phase-2

Chennai Metro Rail Limited (CMRL) has issued a Letter of Acceptance (LoA) to M/s. Linxon India Private for Design, manufacturing, supply, installation, testing, training and commissioning of RSS, ASS, SCADA, OHE & Switching Stations for CMRL Phase II-Corridor 3 (Sholinganallur to SIPCOT 2) & Corridor 5 (from CMBT to Sholinganallur).

  • Tender Reference Number: CMRL/PHASE-II/SYS/C3&5-PS&OHE-10/2021
  • Name of Work: Design, manufacturing, supply, installation, testing, training and commissioning of RSS, ASS, SCADA, OHE & Switching Stations for CMRL Phase II-Corridor 3 (Sholinganallur to SIPCOT 2) & Corridor 5 (from CMBT to Sholinganallur).
  • Accepted Contract Amount: Approx. INR 404.45 Crores
  • Work Completion Period: 1150 Days

In October-2021, the CMRL invited a tender for Tender Number: CMRL/PHASE-II/SYS/C3&5-PS&OHE-10/2021

AACT: 

  • Minimum average annual construction turnover INR 306 Crores calculated as total certified payments received for contracts in progress or completed, within the last 5 (five) years since 1st January 2016, divided by 5 (five) years.

Financial Resources: 

  • The Bidder must demonstrate that its financial resources defined in FIN-3, less its financial obligations for its current contract commitment defined in FIN-4, meet or exceed the total requirements for the subject contract of INR 78 Crores.

Contracts of Similar Size and Nature:

  • Participation as a contractor or Joint Venture (JV) Partner, that have been successfully or substantially completed within the last 10 years (Starting from 1st January 2011) shall  meet the following eligibility criteria: 

A minimum number of:

  • One contract of value INR. 403 Crores or above involving construction of: Power Supply & OHE Contracts in Metro / Railway Projects, or
  • Two contracts of value each INR. 252 Crores or above involving construction of: Power Supply & OHE Contracts in Metro / Railway Projects, or
  • Three contracts of value each INR. 202 Crores or above involving construction of: Power Supply & OHE Contracts in Metro / Railway Projects.

Experience in Key Activities:

  • Contracts completed or under implementation as a contractor (single entity or JV Member) in the last 10 years starting 01st January 2011 in the successful completion of following key activities:
    • FOCS work (25kV and above) of minimum  50km including design, erection, testing and commissioning including at least 1 set of SSP.
    • 33kV and above substation and cable network with at least 5 substations with SCADA system; including  design, erection, testing and commissioning. 
    • 110 kV work (66 kV and above) with at least one substation with SCADA system; including design, erection, testing and commissioning. 
    • SCADA for Traction or Power Supply System for Metro Rail System/ Suburban/ main line Railway Project; including design, erection, testing and commissioning.

About Chennai Metro Phase-2:

  • Phase II expansion has been planned for a length of 118.9 Km network with 128 nos. Of Stations. It consists of three Corridors i.e. Corridor -3 – From Madhavaram to SIPCOT (45.8 Km), Corridor -4 – From Lighthouse to Poonamalle Bypass (26.1 Km), Corridor-5- From Madhavaram to Sholinganallur (47 Km).
  • The estimated cost of the project is Rs. 63246/- Cr (Rupees Sixty three thousand two hundred and forty six only) (including IDC). The project is proposed to be completed by the end of 2026.

Source: CMRL- Tender Update | Image Credit (representational): CMRL