Dedicated Freight Corridor Corporation of India Limited (DFCCIL) has invited open E-Tenders in single packet system for Design, Supply, Erection, Testing and Commissioning of Traction Energy Management System for DFCCIL (New Bhaupur-New Khurja) Section.
Key Details:
- Tender No.: DFCCIL/EL/TDL/BPU-KRJ/TEMS/T-007
- Estimated Cost Of work: Rs. 81.93 Lakh
- Period of Contract: 03 Months
- Date and Time of submission of tender: 23.06.2021, 15:00hrs
- Date and Time of opening of tender: 23.06.2021, 15:30hrs
Scope of Work:
- Traction Energy management system on DFCCIL is to be implemented with provision of Configuration and Time Syncronisation of existing ABT meters at TSS, Supply, Erection, Testing & commissioning of Floor mount, RTU panel at TSS locations and other hardware.
- Traction substations, Umari TSS, Itagaon TSS, Ubati (Shikohabad) TSS, Biruni TSS and Ibrahimpur TSS where Proposed scheme is to be implemented to avail power through Open Access.
- However DFCCIL reserves its right to change the TSS where proposed scheme to be implemented on the need basis.
- In this scheme the real time parameters such Active power, Reactive Power, Voltage, Current, Power factor, Status of High Voltage Circuit Breakers at all DFCCIL/Railway’s drawl points i.e TSS, individually and combined are required to be collected, processed and provided to respective State Load Dispatch Centres (SLDCs).
- The necessary infrastructure for telemetry of digital and analogue signals required to implement the scheme is also to be developed.
Supply of EMS Server as per RDSO specification:
- A dedicated Energy management system (EMS) shall be provided at the Operationalcontrol Centre.
- EMS shall record all energy parameters at HV/LV sides of all the FP/TSS locations in the section.
- EMS shall provide logging, storage and visualization functions for data acquired from the sites.
- Price shall include Supply, Installation, Testing, configuration & Commissioning of two EMS servers (1-Main EMS server & 1-Stand by EMS server) at respective RCCs for storing data related to Energy parameters collected from each TSS.
- EMS server will acquire Energy data from the SCADA server and will update its data bank.
- Energy parameters and switch status to be stored in EMS server.
About DFC:
- In the first phase, DFCCIL is constructing the Western DFC (1504 Route km) and Eastern DFC (1856 route km including PPP section of Sonnagar-Dankuni Section.
- The EDFC starting from Sahnewal near Ludhiana (Punjab) will pass through the states of Punjab, Haryana, Uttar Pradesh, Bihar and Jharkhand to terminate at Dankuni in West Bengal.
- The Western Corridor connecting Dadri in Uttar Pradesh to Jawaharlal Nehru Port (JNPT) in Mumbai will traverse through the states of UP, Haryana, Rajasthan, Gujarat and Maharashtra of WDFC & EDFC (excluding the Sonnagar – Dankuni PPP section) i.e. 2800 route Km will be commissioned by June 2022.
- Dedicated Freight corridor is being seen as a game changer in Economic Development of India.
- Hon’ble Prime Minister Shri Narendra Modi had recently dedicated two sections of DFCCIL on Eastern and Western Corridors to the nation.
- These are Rewari – Madar section on Western corridor and New Khurja- New Bhaupur section on Eastern Dedicated Freight Corridor.
Source: DFCCIL-Tender | Image Credit (reperesentational): DFCCIL