In order to provide seamless inter-station connectivity, the Mumbai Metropolitan Region Development Authority (MMRDA) has issued Letters of Acceptance (LoA) to multiple companies for the implementation of Multi-Modal Integration Facilities at metro stations on Mumbai Metro Line-2B. This initiative aims to streamline passenger movement and improve the overall transit experience.
More Details:
RPS Infraprojects Pvt. Ltd. secures below contract:
- Tender Reference No.: MMRDA/TnC/MMI/2B/PACK 1/2023
- Name of work: Implementation of Multi Modal Integration Facilities at Metro Stations of Mumbai Metro Line-2B (Package-1 (ESIC Nagar to Khira Nagar).
- Awarded Value: Rs. 55,18,71,866.59/-
- Contract Period: 12 Months (Excluding Monsoon+2 Years DLP)
Following Metro Stations are part of Package-1:
- ESIC Nagar
- Prem Nagar
- Indira Nagar
- Nanavati Hospital
- Khira Nagar
N A Construction Pvt. Ltd. secures below contract:
- Tender Reference No.: MMRDA/TnC/MMI/2B/PACK 2/2023
- Name of work: Appointment of contractor for implementation of Multi Modal Integration Facilities at Metro Stations of Mumbai Metro Line-2B (Package-2: Saraswat Nagar to IL and FS).
- Awarded Value: Rs. 63,47,89,658.55/-
- Contract Period: 12 Months (Excluding Monsoon+2 Years DLP)
Following Metro Stations are part of Package-2:
- Saraswat Nagar
- National College
- Bandra Station
- ITO
- IL&FS
R K Madhani and Co secures below contract:
- Tender Reference No.: MMRDA/TnC/MMI/2B/PACK 3/2023
- Name of work: Appointment of Contractor for Implementation of Multi Modal Integration Facilities at Metro Stations of Mumbai Metro Line-2B (Package-3 MTNL to Chembur).
- Awarded Value: Rs. 51,89,33,436.40/-
- Contract Period: 12 Months (Excluding Monsoon+2 Years DLP)
Following Metro Stations are part of Package-3:
- MTNL
- S.G. Barve Marg
- Kurla East
- EEH
- Chembur
Relcon Infraprojects Ltd. secures below contract:
- Tender Reference No.: MMRDA/TnC/MMI/2B/PACK 4/2023
- Name of work: Appointment of Contractor for Implementation of Multi Modal Integration Facilities at Metro Stations of Mumbai Metro Line-2B (Package-4 Diamond Garden to Mandale).
- Awarded Value: Rs. 55,06,26,381.10/-
- Contract Period: 12 Months (Excluding Monsoon+2 Years DLP)
Following Metro Stations are part of Package-4:
- Diamond Garden
- Chhatrapati Shivaji Maharaj Chowk
- BSNL
- Mankhurd
- Mandale
Scope of Work for the Contractors:
The Scope of work includes mainly comprise of improvements/ widening of footpaths in the designated station influence area including Road works, Storm water drain works, development/extension of footpath in the Metro station influence area, providing dedicated drop‐off/ pick‐up bays for buses, feeders, auto/ taxies, private vehicles etc., providing cycle tracks and cycle parking areas, Geometric improvement to Junctions, providing property entry/ exits, providing handrails, lane marking, cat‐eyes etc, and providing traffic management measures along with the junction improvements such as central medians, signals and signage (cautionary & informatory), Tree guards, street furniture (like dust bin, benches, bus stop, Kiosks, bollards, etc), landscaping, street lights(relocation), wayfinding signage, etc. within the Metro station influence area.
Conclusion:
The MMRDA’s initiative for Multi-Modal Integration Facilities on Mumbai Metro Line-2B will greatly improve passenger convenience and connectivity. The scope of work includes widening footpaths, creating dedicated drop-off/pick-up bays, adding cycle tracks, and enhancing junctions, aiming to streamline transit and enhance the overall metro experience.
Source: MMRDA – Tender Update | Image Credit (representational): MMRDA
Join us for the upcoming 5th Rail & Metro Technology Conclave with 700+ Top Rail & Metro Industry Leaders on 23rd & 24th July, 2024 in New Delhi, India. Register here and participate in the summit.