MRIDC invites bids for construction of Road Under Bridges at various locations across Railway Lines in Maharashtra

MRIDC has invited e-bids in two packet systems from eligible tenderers for “Construction of Road Under Bridges (RUB) and Limited Height Subways (LHS) at various locations across Railway Lines in Maharashtra area.”

  • e-Tender No.: MRIDC/PROJ/e-TENDER/RUB-LHS/2021/112
  • Estimated cost of the work: INR 107,63,85,169/-
  • Completion period: 400 days.  

About MRIDC:

  • Maharashtra Rail Infrastructure Development Corporation Limited (MRIDC), is a joint venture company of Govt. of Maharashtra and Ministry of Railways for implementation of various Railway Projects in the territory of Maharashtra.
  • The aim of the company is to provide a boost to the Rail Infrastructure projects in and around  Maharashtra  State.
  • There are several projects of new Railway Lines, Gauge conversion, doubling, Road Over Bridges, Road Under Bridges & Limited Height Subways waiting for implementation.
  • The aim of the company is to take a leap forward in implementing railway related infra projects.

Interested Bidders can download the tender document from MRIDC’S official website www.maharail.com and e-bidding portal www.tenderwizard.in/MAHARAIL.

Recent Tender:

Following are the some of the tenders floated by MRIDC recently:

  • Tender No.: MRIDC/PROJ/e-TENDER/ROB/2021/107
    • Name of work: “Construction of Road Over Bridges (ROBs) at 3 Locations (i.e. Pune-Miraj Section at LC No. 112- km 239/1-2, LC No. 119 – km 256/6-7 and LC No. 465 – km 764/5-6) in Lieu of LC Gates in Maharashtra area on Pune Division of Central Railway.
    • Estimated cost of the work: Rs. 60,57,28,520/-
    • Completion period: 300 days
  • Tender No.: MRIDC/PROJ/e-TENDER/OHE/2021/108
    • Name of work: Supply, Erection Testing and Commissioning of 25 kV, 50 Hz, Single Phase, Traction Overhead Equipment, Traction Substation, Switching station and other associated works from chainage (-) 1.214 to chainage 105.000 & WCL siding, Chord line, loop lines, bridges etc. in connection with Railway Electrification Work between Naghbir to Itwari Section in Nagpur Division of South East Central Railway”
    • Estimated cost of the work (excluding GST): Rs. 59,61,52,775/
    • Completion period: 300 days

Source: MRIDC-Tender | Image Credit (representational): MoR