Mumbai Metro-3 update: Flash Butt Welding Machine arrives from USA begins welding of rails

Share with your network

An important equipment, Flash Butt Welding Machine (FBW Machine), which will weld Head Hardened (HH) rails for the 33.5-km long Colaba-Bandra-SEEPZ Metro-3 corridor, has arrived in Mumbai and begun its work at the Chhatrapati Shivaji Maharaj International Airport Station (CSMIA-T2) on Friday.

  • FBW Machine will weld the rails by aligning, preheating, flashing, forging, stripping and air-quenching at a flash voltage of 340V and Boost Voltage of 420V. 
  • This is first of the two such plants to be deployed. 
  • “This is an automatic welding  machine with pre-set parameters to function exactly as per the set values to produce quality welds. 
  • Welding of rails is planned from eleven different locations to cover entire 33.5km project”, informed Mr. Ranjit Singh Deol, MD, MMRC. 
  • The FBW Machine is manufactured by M/s. Holland LP, USA. 
  • The second FBW Machine is expected by the end of next month.
  • In all 8,366 ton of HH rails, out of 10,740 ton, have already been received by the Mumbai Metro Rail Corporation (MMRC). 
  • Remaining rails are already shipped from Japan. 

“These 18-meter long HH rails, manufactured by M/s. Mitsui, Japan, will be welded into long panels using the FBW Machine and laid as continuously welded rails. For safety and passenger comfort”, said Mr. Subodh Gupta, Director (Projects), MMRC.

Recent Progress:

  • Mumbai Metro Rail Corporation (MMRC) is only nine more breakthroughs away from achieving 100% tunnelling. 
  • The remaining nine breakthroughs will be achieved in package Nos.1, 3, 4 and 6 
  • MMRC has achieved 32 breakthroughs in Package Nos.2 ,5 and 7 – a length of about 48-km out of the total length of 54.5-km. 
  • On 5th October, 2020, MMRC has achieved 32nd breakthrough of 1.10-km long tunnel from Siddhivinayak north shaft to Dadar Metro Station in the presence of Mr. Ashutosh Kumbhakoni, Advocate General of Maharashtra.
  • The Herrenknecht made Tunnel Boring Machine (TBM) Krishna-2, equipped with Earth Pressure Balance technology, was lowered on December 16, 2019.
  • The TBM has completed the upline stretch in 295 days using 791 rings.
  • The overall progress of Dadar Metro Station is 61%.
  • Package-4, which consists of Dadar, Siddhivinayak and Sitladevi Metro Stations, showcases overall 94% tunneling progress and 95% of the excavation work.
  • The total tunneling of the project completed is 87% and civil work is 60% as on 5th Oct, 2020.

Source: MMRC-Press Release | Image Credit: MMRC

Be the first to comment

Leave a Reply

Your email address will not be published.


*