Mumbai Metro-3 Update: MMRC completes tunnelling under Mithi river

Share with your network

The Mumbai Metro Rail Corporation (MMRC) has successfully completed tunnelling under the main channel of the Mithi river for Mumbai Metro Line 3 corridor. Of the 1.18 km, both tunnels have crossed the 270-metre-long active river channel.

More Information:

  • The portion is between BKC and Dharavi station and is part of the 1.48 km tunnels being built between the two stations.
  • The two Tunnel Boring Machines (TBMs) had completed 87% and 65%, and were expected to finish work by the end of March.
  • One TBM has around 200 metres left to tunnel, while the secon has 500 metres remaining.
  • The tunnels are about 8-12 metres below the surface of the water.
  • Mumbai Metro Line-3 project is a 33.5 KMs long underground corridor running along Colaba-Bandra-SEEPZ with 27 key stations out of which 26 will be underground and 1 at grade.
  • Mumbai Metro Rail Corporation Limited (MMRC) is the nodal agency responsible for the implementation of Mumbai Metro Line–3(MML-3) project.