Mumbai Metropolitan Region Development Authority (MMRDA) has invited bids from eligible Bidders through MMRDA e-tendering Portal for Planning & Design of Multi Modal Integration at 11 Metro Stations of Mumbai Metro Line-7A & 9.
- Tender Ref No.: MMRDA/TC/0002457
- Name of Work: Planning and Design of Multi Modal Integration at 11 Metro Stations of Mumbai Metro Line 7A and 9.
- Bid document download: From 03/05/2021 To 18/06/2021
- Pre Bid Meeting by video conference: 13/05/2021
- Last Date of Online submission: From 03/05/2021 To 18/06/2021
- Bid Transfer date: From 18/06/2021 To 21/06/2021
Tender Schedule:
Sr No. | Department Schedule | Supplier Activity | Duration | Start Date and Time | End Date and Time |
1 | Tender Authorization and Publishing | Tender Document Download | 0 Days 50 Minutes | 03/05/2021 02:10 PM | 03/05/2021 03:00 PM |
2 | 45 Days 23 Hours 59 Minutes | 03/05/2021 03:01 PM | 18/06/2021 03:00 PM | ||
3 | 45 Days 23 Hours 59 Minutes | 03/05/2021 03:01 PM |
18/06/2021 03:00 PM | ||
4 | Tender Closing | Bid Preparation and Submission | 0 Days 2 Hours 59 Minutes | 18/06/2021 03:01 PM | 18/06/2021 06:00 PM |
5 | Online Control Transfer of Bid |
2 Days 20 Hours 59 Minutes | 18/06/2021 06:01 PM | 21/06/2021 03:00 PM | |
6 | Opening Envelope A – Tender Fees, EMD | 24 Days 2 Hours 59 Minutes | 21/06/2021 03:01 PM | 15/07/2021 06:00 PM | |
7 | Opening Envelope B – Technical Bid | 24 Days 2 Hours 59 Minutes | 21/06/2021 03:01 PM | 15/07/2021 06:00 PM | |
8 | Opening Envelope C – Financial Bid | 24 Days 2 Hours 59 Minutes | 21/06/2021 03:01 PM |
5/07/2021 06:00 PM |
The e-RFP shall be available for download on registration at https://etendermmrda.maharashtra.gov.in as per the above-mentioned dates. The submission of the e-RFP response is through MMRDA e-tendering Portal only.
About Metro Line 9 (i.e. Line 7 Extension):
- Metro Line 9 is extension of Line 7 form Andheri to CSIA and Dahisar to Mira Bhayander and is 13.581 km long (11.386 km elevated and 2.195km underground) with 11 stations.
- It shall provide interconnectivity among the existing Western Express Highway, Western Railway, ongoing Metro Line 2A (Dahisar to D N Nagar) and Metro Line 7(Andheri (E) to Dahisar (E)).
- It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
- Maintenance Depot has been proposed at Mira-Bhayander (main depot for entire line-7). Total land area proposed for maintenance facilities is 20.0 Ha.
- It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Present Status:
Updates as on 1st March 2021
(Line 9) (Elevated):
Sr. No. | Name of Work | Status in % |
1 | Survey Work | 82% completed. |
2 | Barricading board fixing | 60% completed |
3 | Soil investigation work | 75% completed. |
4 | Utility Identification Works | 57% completed. |
5 | Piling Works | 38 completed. |
6 | Pile cap works | 21% completed. |
7 | Pier Works | 9% completed. |
8 | Pier Cap Casting | 3% completed. |
9 | U-Girder Casting | 0.4% completed. |
10 | Concourse Pierarm | 8% completed. |
11 | Pier Cap Erection | 0.6% completed. |
(Line 7A) (Partly Elevated & Underground): | ||
1 | Survey Work | 100 % completed. |
2 | Barricading board fixing | 15 % completed. |
3 | Soil investigation work | 86 % completed. |
4 | Utility Identification Works | 28% completed. |
5 | Piling Works | 19% completed. |