The Mumbai Metropolitan Region Development Authority (MMRDA) has invited Request for Proposal (RFP) in two packages for Appointment of Project Management Consultant (PMC) for Supervision and Monitoring of Multi-Modal Integration facilities implementation at 15 Stations of Mumbai Metro Line 2A & 7.
The RFP details are as under:
Package 1:
- Tender Ref No: MMRDA/TC/0002393
- Name of Work: Request for Proposal for “Request for Proposal for Appointment of Project Management Consultant(PMC) for Supervision and Monitoring of Multi- Modal Integration facilities implementation at 15 Stations of Mumbai Metro Line 2A and 7 Package 2 3rd Call.
Package 2:
- Tender Ref No: MMRDA/TC/0002394
- Name of Work: Request for Proposal for “Request for Proposal for Appointment of Project Management Consultant(PMC) for Supervision and Monitoring of Multi- Modal Integration facilities implementation at 15 Stations of Mumbai Metro Line 2A and 7 Package 2 3rd Call.
Important Dates:
- Bid document download: From 26.03.2021 To 05.04.2021
- Date of Closing: From 05.04.2021 To 05.04.2021
- Bid Transfer date: From 05.04.2021 To 06.04.2021
Tender Schedule:
Sr No. | Department Schedule | Supplier Activity | Duration | Start Date And Time | End Date And Time |
1 | Tender Authorization and Publishing | 0 Days 15 Hours 44 Minutes | 25/03/2021 05:45 PM | 26/03/2021 09:29 AM | |
2 | Tender Document Download | 10 Days 7 Hours 30 Minutes | 26/03/2021 09:30 AM | 05/04/2021 05:00 PM | |
3 | Bid Preparation and Submission | 10 Days 7 Hours 30 Minutes | 26/03/2021 09:30 AM | 05/04/2021 05:00 PM | |
4 | Tender Closing | 0 Days 59 Minutes | 05/04/2021 05:01 PM | 05/04/2021 06:00 PM | |
5 | Online Control Transfer of Bid | 0 Days 23 Hours 59 Minutes | 05/04/2021 06:01 PM | 06/04/2021 06:00 PM | |
6 | Opening Envelope A – Tender Fees, EMD | 0 Days 8 Hours | 07/04/2021 10:00 AM | 07/04/2021 06:00 PM | |
7 | Opening Envelope B – Technical Bid | 0 Days 8 Hours | 07/04/2021 10:00 AM | 07/04/2021 06:00 PM | |
8 | Opening Envelope C – Financial Bid | 0 Days 8 Hours | 07/04/2021 10:00 AM | 07/04/2021 06:00 PM |
The e-RFP shall be available for free download on registration at https://etendermmrda.maharashtra.gov.in as per the above-mentioned dates. The submission of the e-RFP response is through MMRDA e-tendering Portal only. For participating in this e-RFP and avoiding last minute technical challenges if any, all the bidders shall follow the guidelines mentioned in the e-RFP document on e-tendering Portal. The bidders shall go through the e-tender SOP and FAQs hosted at MMRDA e-tendering Portal for detailed understanding of e-tendering submission process. For any e-tendering support, bidders shall mail MMRDA e-tendering Helpdesk at etendersupport@mailmmrda.maharashtra.gov.in or call Helpdesk on 022-2659 7445.
About Mumbai Metro Line 2A (Dahisar – D.N. Nagar):
- Metro Line 2A from Dahisar to D N Nagar is 18.589 km. long elevated corridor with 17 stations.
- It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Lines 2B (D N Nagar to Mandale) & 7 (Andheri (E) to Dahisar (E)) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
- It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Dahisar and D N Nagar.
- It shall provide connectivity between the Western, Central Mumbai and the Northern suburban Mumbai.
- It shall provide rail based access to the commercial and geographical landmarks in Mumbai.
- It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Present Status:
Updates as on 09th March 2021.
Sr. No. | Name of Work | Status |
1 | Soil Investigation Works | 99.80 % of the soil investigation work for Pier foundation is completed. |
2 | Utility Works | 99.80% completed. |
3 | Piling Works | 99.60% completed. |
4 | Pile Cap Works | 99.40% completed. |
5 | Pier Works | 98.00% completed. |
6 | Pier Cap Works | 99.10% cast and 96.70% erected. |
7 | U Girder Works | 99.90% cast and 97.30% erected. |
8 | Station Work | 82.00% completed. |
About Mumbai Metro Line 7 (Andheri East – Dahisar East):
- Metro Line 7 from Andheri (E) to Dahisar (E) is 16.475 km. long elevated corridor with 13 stations.
- It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Line 2A (Dahisar to D N Nagar) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
- It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Andheri, JVLR and Dahisar.
- It shall provide connectivity between the Central Mumbai and the Northern suburban Mumbai.
- It shall provide rail based access to the Mumbai International Airport (CSIA), SEEPZ, National Park and other commercial and geographical landmarks.
- Dedicated Depot is planned at Dahisar in an extent of 15 Ha.
- It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Present Status:
Updates as on 01th March 2021.
Sr. No. | Name of Work | Status |
1 | Soil Investigation Works | 100 % of the soil investigation work for Pier foundation is completed. |
2 | Utility Works | 99.5% completed. |
3 | Piling Works | 100% completed. |
4 | Pile Cap Works | 100% completed. |
5 | Pier Works | 100% completed. |
6 | Pier Cap Works | 98% Cast and 96 % Erected. |
7 | U Girder Works | 98 % Cast and 90 % Erected. |
8 | I Girder Works | 86 % Cast and 75 % Erected. |
9 | Deck Slab (Via) | 77% completed. |
10 | Station Work | 85.36% completed. |
Source: MMRDA-Tender | Image Credit (representational): BEML