Mumbai Metro update: RFP invited for appointment of Project Management Consultant for Mumbai Metro Line 2A & 7

The Mumbai Metropolitan Region Development Authority (MMRDA) has invited Request for Proposal (RFP) in two packages for Appointment of Project Management Consultant (PMC) for Supervision and Monitoring of Multi-Modal Integration facilities implementation at 15 Stations of Mumbai Metro Line 2A & 7.

The RFP details are as under:

Package 1:

  • Tender Ref No: MMRDA/TC/0002393
  • Name of Work: Request for Proposal for “Request for Proposal for Appointment of Project Management Consultant(PMC) for Supervision and Monitoring of Multi- Modal Integration facilities implementation at 15 Stations of Mumbai Metro Line 2A and 7 Package 2 3rd Call.

Package 2:

  • Tender Ref No: MMRDA/TC/0002394
  • Name of Work: Request for Proposal for “Request for Proposal for Appointment of Project Management Consultant(PMC) for Supervision and Monitoring of Multi- Modal Integration facilities implementation at 15 Stations of Mumbai Metro Line 2A and 7 Package 2 3rd Call.

Important Dates:

  • Bid document download: From 26.03.2021 To 05.04.2021
  • Date of Closing: From 05.04.2021 To 05.04.2021
  • Bid Transfer date: From 05.04.2021 To 06.04.2021

Tender Schedule:

Sr No.Department ScheduleSupplier ActivityDurationStart Date And TimeEnd Date And Time
1Tender Authorization and Publishing0 Days 15 Hours 44 Minutes25/03/2021 05:45 PM26/03/2021 09:29 AM
2Tender Document Download10 Days 7 Hours 30 Minutes26/03/2021 09:30 AM05/04/2021 05:00 PM
3Bid Preparation and Submission10 Days 7 Hours 30 Minutes26/03/2021 09:30 AM05/04/2021 05:00 PM
4Tender Closing0 Days 59 Minutes05/04/2021 05:01 PM05/04/2021 06:00 PM
5Online Control Transfer of Bid0 Days 23 Hours 59 Minutes05/04/2021 06:01 PM06/04/2021 06:00 PM
6Opening Envelope A – Tender Fees, EMD0 Days 8 Hours07/04/2021 10:00 AM07/04/2021 06:00 PM
7Opening Envelope B – Technical Bid0 Days 8 Hours07/04/2021 10:00 AM07/04/2021 06:00 PM
8Opening Envelope C – Financial Bid0 Days 8 Hours07/04/2021 10:00 AM07/04/2021 06:00 PM

The e-RFP shall be available for free download on registration at https://etendermmrda.maharashtra.gov.in as per the above-mentioned dates. The submission of the e-RFP response is through MMRDA e-tendering Portal only. For participating in this e-RFP and avoiding last minute technical challenges if any, all the bidders shall follow the guidelines mentioned in the e-RFP document on e-tendering Portal. The bidders shall go through the e-tender SOP and FAQs hosted at MMRDA e-tendering Portal for detailed understanding of e-tendering submission process. For any e-tendering support, bidders shall mail MMRDA e-tendering Helpdesk at etendersupport@mailmmrda.maharashtra.gov.in or call Helpdesk on 022-2659 7445.

About Mumbai Metro Line 2A (Dahisar – D.N. Nagar):

  • Metro Line 2A from Dahisar to D N Nagar is 18.589 km. long elevated corridor with 17 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Lines 2B (D N Nagar to Mandale) & 7 (Andheri (E) to Dahisar (E)) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Dahisar and D N Nagar.
  • It shall provide connectivity between the Western, Central Mumbai and the Northern suburban Mumbai.
  • It shall provide rail based access to the commercial and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Present Status:

Updates as on 09th March 2021.

Sr. No.Name of WorkStatus
1Soil Investigation Works99.80 % of the soil investigation work for Pier foundation is completed.
2Utility Works99.80% completed.
3Piling Works99.60% completed.
4Pile Cap Works99.40% completed.
5Pier Works98.00% completed.
6Pier Cap Works99.10% cast and 96.70% erected.
7U Girder Works99.90% cast and 97.30% erected.
8Station Work82.00% completed.

About Mumbai Metro Line 7 (Andheri East – Dahisar East):

  • Metro Line 7 from Andheri (E) to Dahisar (E) is 16.475 km. long elevated corridor with 13 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Line 2A (Dahisar to D N Nagar) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Andheri, JVLR and Dahisar.
  • It shall provide connectivity between the Central Mumbai and the Northern suburban Mumbai.
  • It shall provide rail based access to the Mumbai International Airport (CSIA), SEEPZ, National Park and other commercial and geographical landmarks.
  • Dedicated Depot is planned at Dahisar in an extent of 15 Ha.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Present Status:

Updates as on 01th March 2021.

Sr. No.Name of WorkStatus
1Soil Investigation Works100 % of the soil investigation work for Pier foundation is completed.
2Utility Works99.5% completed.
3Piling Works100% completed.
4Pile Cap Works100% completed.
5Pier Works100% completed.
6Pier Cap Works98% Cast and 96 % Erected.
7U Girder Works98 % Cast and 90 % Erected.
8I Girder Works86 % Cast and 75 % Erected.
9Deck Slab (Via)77% completed.
10Station Work85.36% completed.

Source: MMRDA-Tender | Image Credit (representational): BEML