Mumbai Metro update: Tenders invited for balance civil works of elevated viaduct and 5 elevated stations of Metro Line-2B

In continuation to the tender for appointment of contractor for construction of linkway FOBs at Metro Line-7 Stations, the Mumbai Metropolitan Region Development Authority (MMRDA) has now invited open e-tenders from eligible bidders for C102-Part Design and Construction of Balance Works of Package CA06, Elevated Viaduct and 5 Elevated Stations viz. MTNL Metro, S. G. Barve Marg, Kurla East, EEH and Chembur (excluding Architectural Finishing and Pre-Engineered Steel Roof Structure of Stations) from Chainage 46860.384m to Chainage 52729.312 of Line 2B [D.N Nagar-Mandale] of Mumbai Metro Rail Project of MMRDA.

  • Tender Ref No.: MMRDA/Metro-PIU/0002419
  • Name of Work: C102-Part Design and Construction of Balance Works of Package CA06, Elevated Viaduct and 5 Elevated Stations viz. MTNL Metro, S. G. Barve Marg, Kurla East, EEH and Chembur (excluding Architectural Finishing and Pre-Engineered Steel Roof Structure of Stations) from Chainage 46860.384m to Chainage 52729.312 of Line 2B [D.N Nagar-Mandale] of Mumbai Metro Rail Project of MMRDA.
  • Estimated Cost: INR 631.82 Crore
  • Contract Period: 30 Months
  • Pre Bid Meeting: 06/05/2021
  • Bid documents download: From 22/04/2021 To 07/06/2021
  • Last date of Online submission: 09/06/2021

Tender Schedule:

Sr No. Department Schedule Supplier Activity Duration Start Date And Time End Date And Time
1 Tender Authorization and Publishing 0 Days 35 Minutes 22/04/2021 05:55 PM 22/04/2021 06:30 PM
2 Tender Document Download 45 Days 23 Hours 29 Minutes 22/04/2021 06:31 PM 07/06/2021 06:00 PM
3 Bid Preparation and Submission 47 Days 23 Hours 29 Minutes 22/04/2021 06:31 PM 09/06/2021 06:00 PM
4 Tender Closing 0 Days 29 Minutes 09/06/2021 06:01 PM 09/06/2021 06:30 PM
5 Online Control Transfer of Bid 0 Days 23 Hours 29 Minutes 09/06/2021 06:31 PM 10/06/2021 06:00 PM
6 Opening Envelope A – Tender Fees, EMD 0 Days 7 Hours 11/06/2021 11:00 AM 11/06/2021 06:00 PM
7 Opening Envelope B – Technical Bid 0 Days 7 Hours 11/06/2021 11:00 AM 11/06/2021 06:00 PM
8 Opening Envelope C – Financial Bid 0 Days 7 Hours 11/06/2021 11:00 AM 11/06/2021 06:00 PM

Note:- The e-Tender can be downloaded from e-Tendering Portal: https://www.mmrda.maharashtra.gov.in. Any additional information, Corrigendum & help for uploading & downloading the e-tender, may be availed by contacting MMRDAs e-tendering service desk at the following id: etendersupport@mailmmrda.maharashtra.gov.in or call us on 022-26597445. 

For further information if required you may please contact Chief Engineer (Civil), Metro Project Implementation Unit, MMRDA at 022-26547801/022-26547804/ 022-26547802

About Mumbai Metro Line 2B (D.N. Nagar – Mandale)

  • Metro Line 2B from D N Nagar to Mandale is 23.643 km. long elevated corridor with 20 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Eastern Express Highway, Western Railway, Central Railway, Mono Rail, Metro Line 1 (Ghatkopar to Versova) and Metro Line 2A (Dahisar to D N Nagar), Metro Line 4 (Wadala to Kasarvadavali) & Metro Line 3 (Colaba to SEEPZ) under implementation.
  • It shall provide connectivity between the Eastern & Western Suburban Mumbai.
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • Dedicated Depot is planned at Mandale in up to an extent of 22 Ha. land area.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Present Status:

Updates as on 04th Jan 2021

Sr. No. Name of Work Status
1 Soil Investigation Works 72.86% completed.
2 Utility Works 45.25% completed.
3 Pile Group Works 28.20% completed.
4 Pile Cap Works 16.15% completed.
5 Pier Works 6.94% completed.
6 Pier Cap Works Casting – 5.52% completed.

Erection – 2.39 %completed.

7 U Girder Works Casting – 7.91% completed.

Erection – 1.98% completed.

8 Station Work work is in progress at 5 no’s of stations
9 Mandale Depot works 7% completed.

Source: MMRDA-Tender | Image Credit (representational): BEML