Mumbai Metro update: Tenders invited for Supply of ERP System for Mumbai Metro Line 2A & 7

Maha Mumbai Metro Operation Corporation Limited (MMMOCL) has invited bids from eligible Bidders through e-tendering as detailed below.

  • Tender Ref No.: MMRDA/MMMOCL/0002386
  • Name of Work: Design, Supply, Installation, Testing, Integration, Commissioning and Support of Enterprise Resource Planning (ERP) System for Mumbai Metro Line7- Gundavali to Ovaripada & 2A- Dahisar (East) to Andheri (West).
  • Bid Document Download: From 15.03.2021 to 15.04.2021
  • Tender Fees: INR 5900
  • EMD Fees: INR 312000

Tender Schedule:

Sr No. Department Schedule Supplier Activity Duration Start Date And Time End Date And Time
1 Tender Authorization and Publishing 0 Days 6 Hours 12/03/2021 12:00 PM 12/03/2021 06:00 PM
2 Tender Document Download 30 Days 23 Hours 59 Minutes 15/03/2021 06:01 PM 15/04/2021 06:00 PM
3 Bid Preparation and Submission 30 Days 23 Hours 59 Minutes 15/03/2021 06:01 PM 15/04/2021 06:00 PM
4 Tender Closing 0 Days 4 Hours 59 Minutes 16/04/2021 10:01 AM 16/04/2021 03:00 PM
5 Online Control Transfer of Bid 2 Days 19 Hours 59 Minutes 16/04/2021 03:01 PM 19/04/2021 11:00 AM
6 Opening Envelope A – Tender Fees, EMD 0 Days 6 Hours 59 Minutes 19/04/2021 11:01 AM 19/04/2021 06:00 PM
7 Opening Envelope B – Technical Bid 0 Days 6 Hours 59 Minutes 19/04/2021 11:01 AM 19/04/2021 06:00 PM
8 Opening Envelope C – Financial Bid 0 Days 6 Hours 59 Minutes 19/04/2021 11:01 AM 19/04/2021 06:00 PM

The e-Tender can be downloaded from https://etendermmrda.maharashtra.gov.in.

Any additional information & help for uploading & downloading the e-tender may be availed by contacting MMRDAs e-tendering service desk at the following address: etendersupport@mailmmrda.maharashtra.gov.in or call on 022-26597445. The prospective Bidders can ask for writer clarification if any by 26th March 2021 on email address  sushil.chandra@mailmmrda.maharashtra.gov.in and the written clarification will be uploaded by 31st March 2021.

About Mumbai Metro Line 2A (Dahisar – D.N. Nagar):

  • Metro Line 2A from Dahisar to D N Nagar is 18.589 km. long elevated corridor with 17 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Lines 2B (D N Nagar to Mandale) & 7 (Andheri (E) to Dahisar (E)) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Dahisar and D N Nagar.
  • It shall provide connectivity between the Western, Central Mumbai and the Northern suburban Mumbai.
  • It shall provide rail based access to the commercial and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Present Status:

Updates as on 09th March 2021.

Sr. No. Name of Work Status
1 Soil Investigation Works 99.80 % of the soil investigation work for Pier foundation is completed.
2 Utility Works 99.80% completed.
3 Piling Works 99.60% completed.
4 Pile Cap Works 99.40% completed.
5 Pier Works 98.00% completed.
6 Pier Cap Works 99.10% cast and 96.70% erected.
7 U Girder Works 99.90% cast and 97.30% erected.
8 Station Work 82.00% completed.

About Mumbai Metro Line 7 (ANDHERI EAST – DAHISAR EAST):

  • Metro Line 7 from Andheri (E) to Dahisar (E) is 16.475 km. long elevated corridor with 13 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Line 2A (Dahisar to D N Nagar) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Andheri, JVLR and Dahisar.
  • It shall provide connectivity between the Central Mumbai and the Northern suburban Mumbai.
  • It shall provide rail based access to the Mumbai International Airport (CSIA), SEEPZ, National Park and other commercial and geographical landmarks.
  • Dedicated Depot is planned at Dahisar in an extent of 15 Ha.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Present Status:

Updates as on 01th March 2021.

Sr. No. Name of Work Status
1 Soil Investigation Works 100 % of the soil investigation work for Pier foundation is completed.
2 Utility Works 99.5% completed.
3 Piling Works 100% completed.
4 Pile Cap Works 100% completed.
5 Pier Works 100% completed.
6 Pier Cap Works 98% Cast and 96 % Erected.
7 U Girder Works 98 % Cast and 90 % Erected.
8 I Girder Works 86 % Cast and 75 % Erected.
9 Deck Slab (Via) 77% completed.
10 Station Work 85.36% completed.

Source: MMRDA-Tender | Image Credit (representational): MMRDA