Mumbai Metro update: Tenders invited for supply of Integrated Asset Management System for Metro Line 7 and 2A

Maha Mumbai Metro Operation Corporation Limited (MMMOCL) has invited bids from eligible Bidders through e-Tendering as detailed below.

  • Tender Ref No: MMRDA/MMMOCL/0002364
  • Name of Tender/Bid: Design, Supply, Installation, Testing, Integration, Commissioning and Support of Integrated Asset Management System (AMS) for Mumbai Metro Line7- Gundavali to Ovaripada & 2A- Dahisar (East) to Andheri (West). 
  • Bid Document Download: From 24.02.2021 (18.01 hours) To 24.03.2021 (18.00 hours)

Tender Schedule:

Sr No.Department ScheduleSupplier ActivityDurationStart Date And TimeEnd Date And Time
1Tender Authorization and Publishing2 Days 2 Hours 30 Minutes22/02/2021 03:30 PM24/02/2021 06:00 PM
2Tender Document Download27 Days 23 Hours 59 Minutes24/02/2021 06:01 PM24/03/2021 06:00 PM
3Bid Preparation and Submission27 Days 23 Hours 59 Minutes24/02/2021 06:01 PM24/03/2021 06:00 PM
4Tender Closing0 Days 4 Hours 59 Minutes25/03/2021 10:01 AM25/03/2021 03:00 PM
5Online Control Transfer of Bid0 Days 23 Hours 59 Minutes25/03/2021 03:01 PM26/03/2021 03:00 PM
6Opening Envelope A – Tender Fees, EMD0 Days 2 Hours 59 Minutes26/03/2021 03:01 PM26/03/2021 06:00 PM
7Opening Envelope B – Technical Bid0 Days 2 Hours 59 Minutes26/03/2021 03:01 PM26/03/2021 06:00 PM
8Opening Envelope C – Financial Bid0 Days 2 Hours 59 Minutes26/03/2021 03:01 PM26/03/2021 06:00 PM

Any additional information & help for uploading & downloading the e-tender may be availed by contacting MMRDAs e-tendering service desk at the following address: etendersupport@mailmmrda.maharashtra.gov.in or call on 022-26597445. The prospective bidders can ask for written clarifications, if any, by 9th March, 2021 on email address   sushil.chandra@mailmmrda.maharashtra.gov.in and the written clarifications will be uploaded by 12th March, 2021.

The e-Tender can be downloaded from https://etendermmrda.maharashtra.gov.in

About Mumbai Metro Line 2A (Dahisar – D.N. Nagar):

  • Metro Line 2A from Dahisar to D N Nagar is 18.589 km. long elevated corridor with 17 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Lines 2B (D N Nagar to Mandale) & 7 (Andheri (E) to Dahisar (E)) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Dahisar and D N Nagar.
  • It shall provide connectivity between the Western, Central Mumbai and the Northern suburban Mumbai.
  • It shall provide rail based access to the commercial and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Present Status:

Updates as on 06th Jan 2021:-

Sr. No.Name of WorkStatus
1Soil Investigation Works99.80 % of the soil investigation work for Pier foundation is completed.
2Utility Works99.80% completed.
3Piling Works99.50% completed.
4Pile Cap Works99.10% completed.
5Pier Works97.50% completed.
6Pier Cap Works99.10% cast and 96.55% erected.
7U Girder Works99.85% cast and 94.40% erected.
8Station Work78.50% completed.

About Mumbai Metro Line 7 (Andheri East – Dahisar East):

  • Metro Line 7 from Andheri (E) to Dahisar (E) is 16.475 km. long elevated corridor with 13 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Line 2A (Dahisar to D N Nagar) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Andheri, JVLR and Dahisar.
  • It shall provide connectivity between the Central Mumbai and the Northern suburban Mumbai.
  • It shall provide rail based access to the Mumbai International Airport (CSIA), SEEPZ, National Park and other commercial and geographical landmarks.
  • Dedicated Depot is planned at Dahisar in an extent of 15 Ha.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Present Status: 

Updates as on 01th Feb 2021:-

Sr. No.Name of WorkStatus
1Soil Investigation Works100 % of the soil investigation work for Pier foundation is completed.
2Utility Works99.5% completed.
3Piling Works100% completed.
4Pile Cap Works100% completed.
5Pier Works99% completed.
6Pier Cap Works96 % Cast and 93 % Erected.
7U Girder Works95 % Cast and 87 % Erected.
8I Girder Works85 % Cast and 70 % Erected.
9Deck Slab (Via)77% completed.
10Station Work83.02% completed.

Source: MMRDA-Tender | Image Credit (representational): MMRDA