Mumbai Monorail Update: RFP invited for appointment of consultant for procurement of Rolling Stock

Share with your network

Mumbai Metropolitan Region Development Authority (MMRDA) has invited Request for Proposal (RFP) from eligible bidders through MMRDA e-tendering Portal for Appointment of Consultant for the Procurement of Rolling Stock for Mumbai Monorail Project Including Review of Design and Technical Support during the Lifecycle of Procurement.

  • Tender Ref No: MMRDA/Mono-Piu/0002725
  • Name of Work: Appointment of Consultant for the Procurement of Rolling Stock for Mumbai Monorail Project Including Review of Design and Technical Support during the Lifecycle of Procurement
  • Completion period of the Work: 28 Months
  • Sale of tender documents: From 26/02/2021 to 21/03/2022
  • Last Date of Submission of Tender online: 21/03/2022
  • Date of opening of Tender online: 22/03/2022

Tender Schedule:

Sr No. Department Schedule Supplier Activity Duration Start Date and Time End Date and Time
1 Tender Authorization and Publishing 0 Days 19 Hours 10 Minutes 25/02/2022 26/02/2022
2 Tender Document Download 23 Days 2 Hours 59 Minutes 26/02/2022 21/03/2022
3 Bid Preparation and Submission 23 Days 2 Hours 59 Minutes 26/02/2022 21/03/2022
4 Tender Closing 0 Days 1 Hours 59 Minutes 21/03/2022 21/03/2022
5 Online Control Transfer of Bid 0 Days 20 Hours 59 Minutes 21/03/2022 22/03/2022
6 Opening Envelope A – Tender Fees, EMD 24 Days 2 Hours 59 Minutes 22/03/2022 15/04/2022
7 Opening Envelope B – Technical Bid 24 Days 2 Hours 59 Minutes 22/03/2022 15/04/2022
8 Opening Envelope C – Financial Bid 24 Days 2 Hours 59 Minutes 22/03/2022 15/04/2022
9 Tender Award

About Mono Monorail:

  • Bus services operate in crowded and narrow roads with very low average speed thus reducing commuter benefits wherein buses also add to traffic congestion.
  • Where the systems like Metro or BRT cannot be implemented, Monorail can be easily implemented and can negotiate sharp turns and climb up and down steep gradients easily. 
  • The decision to introduce Chembur – Wadala – Sant Gadge Maharaj Chowk – 20 Km long Monorail corridor, as a feeder service to the other Transit System and to cater crowded and narrow congested areas was taken by the Authority in its 119th meeting held on 28th September, 2007.
  • MMRDA appointed M/s. RITES as a consultant for preparation of Techno-Economic feasibility report as well as providing assistance in Bid process management. 
  • The Techno – Economic and Financial Feasibility study for the project was completed by M/s. RITES and a notification dated 4th November, 2008 was published by Government of Maharashtra for implementation of the project under Tramway Act. 
  • Through global bidding process consortium of L&T and Scomi Engineering, Bhd. were appointed as contractors for implementation.

Tender document can only be obtained online after registration of bidder on the e-tendering portal of MMRDA. For further information in this regard bidders are advised to contact MMRDAs e-tendering service desk at the following id: etendersupport@mailmmrda.maharashtra.gov.in. or at Phone No.: 0222406 5166.


Source: MMRDA-Tender | Image Credit (representational): MMRDA