Commissioner of Railway Safety (CRS)/NF circle has completed the statutory inspection of double line between Dudhnai and Dhupdhara stations commissioned to augment sectional capacity significantly.
More Details:
- The Commissioner of Railway Safety (CRS)/NF circle has completed the statutory inspection of the newly laid double line between Dudhnai & Dhupdhara stations on 24th November, 2022.
- This newly laid second line will be utilized for goods and passenger traffic with a maximum speed of 100 km per hour.
- The entire length of New Bongaigaon – Kamakhya via Goalpara doubling project is of 176 km. The stretch between Dudhnai to Dhupdhara is of 29.71 km.
- Speed trial at 122 km per hour was done by the Commissioner of Railway Safety (CRS)/NF circle.
- Modern technologies like, robust track structure with use of all wide base Pre-Stressed Concrete (PSC) sleepers & Thick Web Switches which is new design of sturdier switches on pre-stressed concrete sleepers and can handle higher speeds were used for this double line territory.
- It is to be mentioned here that with the laying of double lines, movement of trains can be done in both directions without stop-over crossings at stations which will increase the punctuality of trains. More trains can be run with enhanced speed.
- Earlier 26.43 km section between Abhaypuri to Pancharatna was commissioned on 28th July, 2022, on completion of this entire section of New Bongaigaon – Kamakhya via Goalpara, the northeast connectivity will be boosted significantly.
Source: Northeast Frontier Railway- Press Release | Image Credit (representational): MoR