Rail Vikas Nigam Limited (RVNL) for achieving the 18th km of Tunnelling on 12.11.2021 in the most challenging geology on the Rishikesh-Karnaprayag New Rail line project in a remarkably short span of 11 days.
About Rishikesh-Karnaprayag Project:
- The Project, entrusted to Rail Vikas Nigam Limited, proposes to bring rail connectivity to the higher reaches of Uttarakhand.
- The electrified BG rail line will connect important towns like Devprayag, Srinagar, Rudraprayag, Gauchar, and Karnaprayag (5 districts).
- This is a technically challenging project involving the construction of a rail line in the rugged Himalayan topography with complex geology and with 83.08% of the total stretch of 125km rail line lying in tunnels (total 17 tunnels).
- The first station, Yog Nagari Rishikesh station was commissioned in March 2020.
- 5 Adit tunnels have been completed and one of the three major Rail Bridges, over river Chandrabhaga Ji at Rishikesh, has been completed.
- Construction of the other two bridges over river Alaknanda at Lachmoli and Srinagar, respectively, is in progress.
- The team has notched a new benchmark in completing the 18th km of tunneling on 12.11.2021 in the most complex geology in a remarkably short span of 11 days.
- Project completion is planned for 2024-25.
Recent Achievements:
Recently, the Rail Vikas Nigam Limited team has achieved a milestone of doubling the 26.33 km Washimbe Bhalwani section of the Daund-Gulbarga doubling project. A great capacity addition project to the Golden Quadrilateral route.
- Doubling work in Washimbe Bhalwani section (26.33 km) of the Daund-Gulbarga doubling project has been inspected by Shri Manoj Arora Commissioner of Railway Safety Central Circle, Mumbai on 26.10.2021 & 27.10.2021.
- The doubling work included the construction of 65 bridges, three new station buildings at Jeur, Pophlaj, and Washimbe stations, and a new Electronic interlocking at 4 stations.
- With commissioning, a major bottleneck at Pophlaj station where trains were being reversed for crossing on this single line stretch on golden quadrilateral is being eliminated.
- This completes 196.43kms of doubling out of 224.91.
- The section is now operational for train services.
About RVNL:
- The company began its operation in 2005 with the appointment of a Board of Directors.
- The company was granted Miniratna status in September 2013.
- RVNL has been rated “Excellent” for the 9 successive years by the Department of Public Enterprises.
- RVNL has also been ranked 1st amongst the Railway PSEs for the 4 times out of the last 5 years.
- The turnover of the company for the financial year 2019-20 has increased by 44.44%.
- The authorized share capital of the company is Rs. 3000 cr. with paid up share capital of Rs. 2085 cr.
- The company has been listed after its disinvestment of its stake of 12.16% of the company through IPO.
Source: RVNL-Update
Be the first to comment