SWR gets highest ever allocation of Rs 3,245 crore in budget 2021-22

South Western Railway (SWR) is set to complete 2 key existing projects Yalahanka – Penukonda & Arsikere – Tumkur by Mar. 2022. Substantial Increase in allocations to doubling (178 %) road safety works Level crossings (67% ) passenger amenities (25% ) compared to Last Year.

  • SWR to spend a record Rs.3,245 Cr. in the ensuing financial year o­n capital expenditure includes EBR (IF) -Rs.881 Cr and EBR(IRFC)-Rs.137 Cr.
  • Total grant to SWR increased by Rs.536 Cr. i.e 20 % over last year.
  • Highest ever Budget grant of Rs. 4468 Cr.  which is higher than that of last year by  12 % ( with Rs.1,223 Cr. expected as deposit from Govt of Karnataka towards New lines and ROB/RUB).
  • In a paradigm shift, Railways will be focusing on  completion of priority projects quickly.
  • Budget 2021 is Part of the National Rail Plan and making Railways Future ready.
  • Budgetary Grant (BG) under major plan heads:
Plan HeadBG 2020-21 (in Rs. Cr.)BG 2021-22 (in Rs. Cr.)% increase
15Doubling85 {1040 including EBR (IF) & EBR (IRFC) }236 {1254 including EBR (IF) & EBR (IRFC) }178%
29Road Safety Works -Level Crossings213567%
30Safety   Road Over/Under Bridges15817410%
31Track Renewals41048017%
32Bridge works203050%
33Signal and Telecommunication  Works2369200%
36Other Electrical Works517240%
41Machinery & Plant243233%
53Passenger Amenities12215325%
Total Budget Grant1754222727%
EBR-IF79588111%
  • Budget Grant for the year 2021-22 for important o­ngoing works:
Plan HeadSectionProposed outlay 2021-22 (In Rs. Cr)
New LineRayadurg – Tumkur via Kalyandurg (213 Km)250
Bagalkot-Kudachi (142 Km)25
Tumkur-Chitradurg-Davangere (199 Km)100
Gadag – Wadi(252 Km)100
Shivamogga-Shikaripura-Ranebennur (103 Km)100
Belagavi-Dharwad via Kittur (73Km)50
DoublingHospet-Hubballi-Londa-Tinaighat-Vasco-da-Gama365
Hotgi-Kudgi-Gadag165
Yalahanka-Penukonda160
Hubli – Chikjajur336
Arsikere-Tumkur47
Yesvantpur-Channasandra71
Penukonda-Dharmavaram10
Baiyyappanahalli-Hosur80
QuadruplingBengaluru -Whitefield78
Development of coaching depot at Koteganguru12
Traffic FacilitiesBangalore Division – 3rd coaching terminal at Baiyyappannahalli31
Naganahalli – Development of satellite terminal20
  • Important New Works Sanctioned are as under:
Pink Book item No.Track RenewalsSanctioned Cost
365South Western Railway – Primary Track Renewal namely TRR & TSR (Umbrella Work 2021-22)99.66
366South Western Railway – Complete Track Renewal (Primary) (Umbrella Work 2021-22)63.63
367South Western Railway – Through Fastening renewal , Through Ballast renewal, Through Formation Treatment, ISD, TBTR and Through Weld Renewal etc. (Umbrella Work 2021-22)173.45
368South Western Railway – Through Turnout Renewal, Renewal of SEJs, Glued Joints etc. (Umbrella Work 2021-22)59.43
369South Western Railway – Secondary Track Renewal namely CTR, TRR & TSR (Umbrella Work 2021-22)69.80
Bridge Works
393South Western Railway – Repl of girders / slabs, rehabilitation / strengthening of sub-structure & super structure, rebuilding of bridges, bridge protection works, instrumentation & monitoring of bridges, addl waterway and protection work at vulnerable cutting locations (Umbrella Work 2021-22)100
Other Works
424Repl / maintenance works of general services over Indian Railways (Umbrella Work 2021-22)over IR30
Acquisition of CNC surface wheel lathe  at Bengaluru, SGT83.9
  • Budget Grant for the year 2021-22 for important o­ngoing Electrification works is as under:
SectionBG * ( In Rs. Cr)
Hospet-Hubli-Vasco da Gama (346 km)85
Miraj – Londa(189 km)80.14
Birur – Talguppa (161 km)43.89
Bengaluru – Omalur via Hosur (196 km)20
Hospet – Swamihalli (59 km)14.72
Mysuru-Hassan-Mangalore (347 km) Incl. Arsikere – Hassan112.32
Mysuru – Chamarajanagar (61 km)17.83
Chikbanavar- Hassan (166 km)50.06
Kadur – Chikmagaluru (46 km)5.89
Chikjajuru – Ballari (184 km)30
Bangarapet – Yelahanka (149)32.33

Highlights:

  • SWR received a total budget grant of Rs. 3,245 Cr. from the Ministry of Railways  (including  EBR (IF),EBR(IRFC) etc. ),which is the highest ever grant , after formation of the zone in 2003.
  • Bengaluru Suburban:
    • Under pink book of Northern Railway, budget grant of Rs.800 Cr. has been set aside for “Equity infusion into joint ventures (with state governments)”. Presently two JVs are executing major projects – o­ne in Haryana of project cost of Rs. 5000 Cr. plus and o­ne in Karnataka of Rs. .18000 Cr.+ The project in Karnataka is   Bengaluru Suburban being executed by KRIDE, a joint venture of Ministry of Railways and State Government of Karnataka. For this project which minimum   of Rs 300 Cr will be allotted by Ministry of Railways. Equivalent Amount from Government of Karnataka is also expected apart from loans from market.
    • As emphasized by Hon’ble MR in last review meeting of Bengaluru  Suburban project, this is o­ne of the top most priority projects of Railways , will be given tremendous thrust and  any amount of capital will be pumped into the project as per requirement and pace of work.
  • 105 Km of doubling completed and 66 Km planned this year. 203 Km doubling targeted in 2021-22
  • 110 Rkm of electrification completed and 309 Rkm planned this year. 849 Rkm targeted in 2021-22.
  • Along with these major Projects, for the convenience of Public, SWR has constructed 6 ROBs and 31 RUBs.  SWR is set to complete 3 more ROB and 10 RUB/Subways this year which will help public.
  • Shri Ajay Kumar Singh, GM/SWR opined that this budget is historic, considering the huge investment for creating Railways in accordance with National Rail Plan.  He said that several o­ngoing infrastructure works will get impetus with 20% increased allotment.

Source: South Western Railway-Press Release | Image Credit (representational): South Western Railway