MAHSR Update: Completion of 100 Kms of Pier Work in the state of Gujarat

Mumbai-Ahmedabad High Speed Rail Corridor has achieved a milestone of completing 100 kms of pier work in the state of Gujarat (352 Kms).

More details:

Other details are as follows:

  • Project Update in Gujarat State;
  • Piers have been constructed over a stretch of 100 km
  • Pile has been cast over a length of 193 km
  • 9.2 km of viaduct is completed which includes 2.5 km of continuous viaduct near Navsari and 6.7 km erected at different locations.
  • Girder Casting – 22.7 km girders have been cast and 9.2 km girders have been erected.

  • Construction work has started in full swing all along the alignment passing through 8 districts of Gujarat & DNH.
  • The works on 8 HSR Stations from Vapi to Sabarmati are under various stages of construction.
  • Bridge Works on important rivers viz., Narmada, Tapti, Mahi and Sabarmati are in progress.

Land Acquisition Status:

  • Overall: – 97.82%
  • Gujarat: – 98.87%
  • DNH: – 100%
  • Maharashtra: – 95.45%
  • Status of Possession of Land in Maharashtra is 73.83 %

Source: NHSRC- Press Release | Images Credit: MoR