Mumbai Metro update: Tenders invited for supply of telecommunication systems for Main Lines and Depot of Line 4 and extension corridor

The Mumbai Metropolitan Region Development Authority (MMRDA) has invited open e-tenders from eligible bidders for supply and commissioning of Telecommunication system for Main Lines and Depot of Line 4 and extension corridor (Wadala-Kasarvadavali-Gaimukh) of Mumbai Metro Rail Project.

  • Tender Ref No.: MMRDA/4 & 4A/CA76
  • Name of work: Design, Manufacture, Supply, Installation, Testing, and Commissioning of Telecommunication system for Main Lines and Depot of Line 4 and extension corridor (Wadala-Kasarvadavali-Gaimukh) of Mumbai Metro Rail Project of MMRDA.
  • Tender Security (EMD): INR 10.50 Million
  • Completion period of the Work: 133 Weeks
  • Pre-Bid Meeting: 07.04.2021
  • Date & Time of Submission: 18.05.2021
  • Cost of Tender Document Interested Bidders have to make online payment of INR 5,000+GST (@18%) Non Refundable as Tender Processing Fee using online payment gateway during bid preparation using Debit Card/Credit Card/Net-Banking for each of the contract package. 
  • Sale of Tender Document: From 16.03.2021 to 18.05.2021 (up to 12:00 hrs.) on e-tendering portal https://etendermmrda.maharashtra.gov.in for above contract packages.
  • Date & Time of opening of Envelope A, B & C: 19.05.2021

Tenderers are requested to note that this tender is being invited through e-procurement. Tender documents can only be obtained online from MMRDA e-Tendering Portal: https://etendermmrda.maharashtra.gov.in. For detailed information and subsequent Addendum / Corrigendum (if any), please log on to above e-Tendering Portal.

For any additional information & help for uploading & downloading the e-Tender, please contact MMRDA’s eTendering service desk at the following id: etendersupport@mailmmrda.maharashtra.gov.in Phone No.: 022- 26597445

In case of any query / clarifications, tenderers are requested to contact the Director (System), Metro Project Implementation Unit, MMRDA at 022-26597552.

About Mumbai Metro Line 4 and 4A (Wadala-Kasarvadavali-Gaimukh):

  • Metro Line 4 from Wadala to Kasarvadavali is 32.32 km. long elevated corridor with 32 stations.
  • It shall provide interconnectivity among the existing Eastern Express Roadway, Central Railway, Mono Rail, the ongoing Metro Line 2B (D N Nagar to Mandale), and the proposed Metro Line 5 (Thane to Kalyan), Metro Line 6 (Swami Samarth Nagar to Vikhroli) & Metro Line 8 (Wadala to General Post Office).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • Dedicated Depots are planned in Owale land in up to an extent of 20 Ha. and in Godrej Land in up to 15.50 Ha. Area.and Maintenance Depothas been proposed near Gaimukh Station. Area of depot land will be about 23.1 Ha.This depot will serve entire corridor from Wadala to Gaimukh.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Present Status:

Updates as on 01st Feb 2021.

Sr. No.Name of WorkStatus in %
1Soil Investigation Works91.5% of the Soil Investigation work for Pier foundation is completed.
2Utility Works82% completed.
3Piling Works60% completed.
4Pile Cap Works47% completed.
5Pile Works40% completed.
6Pier Cap Works43% Casting completed.

34% Erection completed.

7U Girder Works for Viaduct36 % Casting completed.

21% Erection completed.


Source: MMRDA-Tender