MMRDA floats tender for 4.43 MW of Rooftop Solar at Mumbai Metro Station

The Mumbai Metropolitan Region Development Authority (MMRDA) has floated a tender for 4.43 MW of rooftop solar projects at a station site of the Mumbai Metro Rail Project. The work is expected to be completed within 15 months from the date of issue of the letter of approval (LOA).

More Information:

  • The scope of work includes the design, engineering, manufacturing, supply, storage, civil work, erection, testing and commissioning of the rooftop solar project at Lines 7 and 2A of the Mumbai Metro Rail Project under the Renewable Energy Service Companies (RESCO) model for 25 years.
  • Bidders are also expected to operate and maintain the project in this period.
  • The RESCO model is a system where the solar project is owned by the developer, and the consumer only pays for the energy generated.
  • Tender Security amount is INR 9.96 Lakhs.
  • The last date for the submission of bids is March 26, 2020.