Chennai Metro update: Over 80,152 passengers travelled in Metro after inauguration of Phase-I extension

After the inauguration of Phase-I Extension from Vtlashennanpet to Wimeo Nagar 80,152 passengers have travelled in Chennai Metro Train on 15.02.2021. 

A total of 9,972 passengers have travelled in the Phase-I Extension on 15.022021.

Station Name Passenger Flow 
Wimco Nagar Metro1727 
Thiruvottiyur Metro 1544
Kaladipet Metro 1645
Tollgate Metro1276 
New Washermenpet Metro1466 
Tondiarpet Metro 854
Thiyagaraya College Metro 1460 
Total 9972 

The following metro stations have the highest number of commuters are travelled: 

Corridor-1 Blue Line: 

Station Name Passenger Flow
Airport Metro4791
High Court Metro3806 
Guindy Metro3140 
Thousand Lights Metro2647 
Government Estate Metro2620
Washermanpet Metro2578 
Meenambakkam Metro2425
LIC Metro 2023 

Corridor-2 Green Line:

Station NamePassenger Flow
Central Metro7562 
Thirumangalam Metro 4320
Koyambedu Metro 3339
Alandur Metro 3249 
CMBT Metro 2980
Vadapalani Metro 2514 
Ashok Nagar Metro 1878
Egmore Metro 1836 

Recent Progress: 

The Prime Minister, Shri Narendra Modi inaugurated on 14.02.2021 the 9 kilometre extension stretch of the Chennai Metro Rail Phase-1. The Prime Minister informed that the project has been completed on schedule despite the pandemic. 

  • The project is in line with the boost to Aatmnirbhar Bharat as the rolling stock has been procured locally and civil construction activities were done by Indian Contractors. 
  • Shri Modi mentioned that in this year’s budget, over Rupees Sixty Three thousand crore have been set aside for a hundred and nineteen kilometres of Phase two of the project. 
  • This is one of the largest projects sanctioned for any city in one-go. 
  • The focus on urban transport will boost ‘Ease of Living’ for citizens here, Shri Modi pointed out.
  • The Prime Minister said that improved connectivity brings convenience. 

Source: CMRL-Press Release | Image Credit: CMRL