Kolkata Metro update: Bids invited for Track works for elevated viaduct portion from Nicco Park to Titumir

Rail Vikas Nigam Limited (RVNL) has invited bids under single stage two packet system for the work of “Construction of Double Line Ballast Less Track ( BLT) for Elevated Viaduct Portion Between Nicco Park Having Ch. (13841.585 M) to Titumir Ch. (25891.527 M) including Points and Crossings, etc. In Connection with Construction of Metro Railway Corridor from New Garia to Airport Corridor, in the City of Kolkata”. 

  • Tender Reference Number: RVNL/KOL/NGA-AIRPORT/METRO/BLT /NICCO PARK-TITUMIR
  • Approx. Estimated Cost of Project: INR 130.48 Crores
  • Bid Security: INR 2 Crores
  • Period of Completion: 24 Months 
  • Pre Bid Meeting Date: 24-Feb-2021
  • Document Download / Sale Start Date: 08-Feb-2021
  • Document Download / Sale End Date: 26-Mar-2021
  • Bid Submission Start Date: 10-Mar-2021
  • Bid Submission End Date: 26-Mar-2021
  • Bid Opening Date: 26-Mar-2021

Scope of Work:

This work pertains to “Construction Of Double Line Ballast Less Track (BLT) For Elevated Viaduct Portion Between Nicco Park Having Ch. (13841.585 M) To Titumir Ch.(25891.527 M) Including Points And Crossings, etc. In Connection With Construction Of Metro Railway Corridor From New Garia To Airport Corridor, In The City Of Kolkata”. Proposed work consists of construction of double line ballast less track over Elevated viaduct for a length of approximate 12.875 km.

  • Out of total12.875 KM length of BLT (Viaduct + Station portion), about 9.88 Km of Viaduct & 3 Stations are ready for immediate laying of BLT. Available ready locations of viaduct stretches are given below:
Location PIER IDLength (Mtr)Remarks
FromTo
P383P4231150
P424P459844
CP482P504634
Bidhan nagar Station180Track slab complete
P505P5341091Incld. SP514 to SP522
SUB CBD 1 Station180Track slab complete
P537PP574C1091
P578P601606.3
Kalkhetra Station180Track slab complete
P601AP6441195.458
P668P681356
P682P7201135.535
P721P745574.829
SP725PP736302
P746CP760367
9887.122
  • 6.0 (Six) Route Km of BLT works out of the above available location (viaduct & station) to be completed in 12 months. For the balance stretches of viaduct between chainage 15415.509M (P428) to 17020.00M (CP481) and construction work (except Technopolis station from chainage16260.739M to 16440.739M) are already in progress through different contracts. 
  • Balance site of work (approximately 2988 M) would be provided in phases after completion of initial 12 months as and when it is ready for laying of BLT work. 
  • Participating bidder(s) has to consider this aspect while quoting their offer. Planning for completion of the work to be synchronized according to the site available/handed over to the construction contractor. 
  • Nothing extra shall be paid over and above the accepted rate of BOQ items for repeated demobilization/re-mobilization of plants, equipment, all kind of resources etc. to complete the entire BLT work from chainage 13841.585 M to 25891.527 M in peace meal/ stretches. 

b) Broad Scope of Present Tender:

Salient features of the proposed BLT work are as under:

Sr. No.Description
1Construction of RCC M50 Track plinth for BLT including provision for 3rd rail.12.875 route Km (25.751 Track Km).
2Supply of Track fastening assembly for BLT track on Metro Railways as per Railway Board’s performance criteria circulated vide Railway Bd. Letter no.2009/Proj/MAS/9/2 dt. 18.02.2015.a) With two bolts-52648 nos. rail seat assembly.

b) With four bolts30030 nos. rail seat assembly.

3Laying of BLT track with 60KG rails adopting top-down method.12.875 route Km.
4Supply, Design, Manufacture & Laying in position turnouts ,Diamond Crossing & Derailing Switch assembly for BLT.24 Sets -1/12

2 Sets- Derailing Switch

1 Set – Diamond Crossing

2 Set -1/8.5 T/ Os

5Supply of other track fittingsFor 12.875 route Km of BLT.

Bidding Documents can be downloaded free of cost from RVNL website www.rvnl.org and RVNL e- Tendering portal i.e. https://rvnl.euniwizarde.com


Source: RVNL-Tender | Image Credit (representational): Metro Railway, Kolkata