
Mumbai Metro Rail Corporation (MMRC), on Monday achieved 32nd breakthrough of 1.10-km long tunnel from Siddhivinayak north shaft to Dadar Metro Station in the presence of Mr. Ashutosh Kumbhakoni, Advocate General of Maharashtra. He said, “I appreciate that a monumental task is being completed while causing as little inconvenience to the public as possible. This line will be an important addition to the public transport infrastructure and a boon to Mumbaikars”.
- The Herrenknecht made Tunnel Boring Machine (TBM) Krishna-2, equipped with Earth Pressure Balance technology, was lowered on December 16, 2019.
- The TBM has completed the upline stretch in 295 days using 791 rings.
“Today’s breakthrough was a challenging task as Dadar Metro Station – one of the more prominent stations on the Colaba-Bandra-SEEPZ corridor – is located in close proximity of residential buildings and commercial shops”, said Mr. Ranjit Singh Deol, Managing Director, MMRC.
- The overall progress of Dadar Metro Station is 61%.
- Package-4, which consists of Dadar, Siddhivinayak and Shitladevi Metro Stations, showcases overall 94% tunneling progress and 95% of the excavation work.
- The total tunneling of the project completed is 87% and civil work is 60% as on 5th Oct, 2020.
Recent Progress:
MMRC on 21st September, 2020 achieved its 31st breakthrough of the 1.5-km long tunnel from Sahar to CSIA T1 station. Terratec-made Dual mode hard rock Tunnel Boring Machine (TBM) Tapi-1 completed the downline stretch in 449 days using 1080 rings.
- The overall progress of CSIA T1 station is 55%.
- Package-6, which consists of CSIA T1, T2 and Sahar Road stations, showcases overall 85% tunnelling.
- The total tunnelling of the project completed is 87% and civil work is 60%.
- There are few more breakthroughs to be achieved on the project in coming months as 7 TBMs are on work in different areas.
Source: MMRC-Press Release | Image Credit: MMRC
Be the first to comment