Railway Board Chairman & CEO Smt. Jaya Varma Sinha inspects USBRL Project in Jammu & Kashmir

In a significant development for Indian Railways, Smt. Jaya Varma Sinha, Chairman & Chief Executive Officer of the Railway Board, undertook a comprehensive inspection of the USBRL Project in Jammu & Kashmir, emphasising the criticality of connecting the Kashmir Valley to the national railway network.

Image Credit: Northern Railway

More Details:

Smt. Jaya Varma Sinha, Chairman & Chief Executive Officer, Railway Board has carried out an intensive inspection of the USBRL project o­n 09.02.2024. Shri Shobhan Chaudhuri, General Manager/Northern Railway, Shri Sandeep Gupta, CAO/USBRL, Shri Sanjay Gupta, CMD/KRCL, Shri V. P. Singh, PCE/NR, Shri U. C. Joshi, PCOM/NR & Sanjay Sahu, Divisional Railway Manager/Firozpur and other senior officers of USBRL Project were present during the inspection. Emphasise to expedite the remaining work of the project.

Image Credit (representational): MoR

During Inspection:

  • She commenced inspection from Katra to Tunnel No. T-33 (old T-1). She conducted Motor Trolly inspection, followed by an intensive o­n foot inspection of o­ngoing critical work of Tunnel T-33.
  • She appreciated the good work being done by the project team under the extremely challenging geological conditions and advised them to follow all safety protocols.
  • She directed the project authorities to take all possible measures to expedite the completion of balance works so that the Katra-Reasi section can be linked.

Image Credit (representational): MoR
  • She continued the motor trolley inspection Tunnel T-34 (old T-2) o­nwards through Anji Bridge, Reasi Station, Bakkal Station, Chenab Bridge right up to Dugga railway station inspecting track, E&M, S&T and RE works and expressed satisfaction regarding the quality and progress of these works. 
  • CRB reviewed the progress of the USBRL project at Chenab Bridge site with the officials of NR, KRCL & IRCON.
  • She expressed satisfaction at the pace of works and directed the project authorities to closely monitor all balance works especially Tunnel T-1 & Sawalkote yard works to ensure that there are no delays.

Image Credit (representational): MoR

Significance

  • Despite facing various geological, topographical, and meteorological challenges, the USBRL project continues to progress steadily, bringing the dream of connecting Kashmir Valley to the national railway network closer to realisation.
  • Smt. Jaya Varma Sinha’s visit underscores Indian Railways’ commitment to enhancing connectivity and infrastructure development in the region, promising improved accessibility and opportunities for residents.

Image Credit: Northern Railway

The relentless efforts of Indian Railways towards completing the USBRL project highlight its dedication to fostering connectivity and development in Jammu & Kashmir, signalling a promising future for the region’s transportation landscape.

Image Credit: Northern Railway

Source: Northern Railway- Press Release | Featured Image Credit: Northern Railway