South Central Railway (SCR) has started the New Year by achieving a landmark achievement by drastically enhancing the maximum speed to 130 kmph for 1,280 km length out of 1,612 Km in Golden Quadrilateral – Golden Diagonal (GQ-GD) route. This covers the entire GQ-GD route over SCR, except Vijayawada – Duvvada section, where signaling up-gradation work is in progress.
- The enhanced speed limits could be achieved due to the systematic and planned strengthening of track & its infrastructure by removing bottlenecks in these sections on a fast pace.
- This included heavier rails, laying of 260 meters Long welded rail panels, improvement of curves and gradients among others.
- The Zone has utilized the opportunity of the Lockdown period and low train movement last year (due to the Covid-19 pandemic) to complete all necessary infrastructure up-gradation works.
- Based on these improvements done by the Zone, the RDSO/Lucknow conducted oscillation trials through Confirmatory Oscillograph Car Run (COCR) consisting of instrumented coaches of all classes at 130 Kmph speed during July and October last year.
- During this check, in addition to track parameters, other areas like Signaling aspect, Traction distribution equipment, Locomotive & coach fitness were also checked and recorded.
- Accordingly, the zone has received sanction to enhance the maximum speed limits to 130 kmph along the following routes:
- Golden Diagonal (Grand Trunk) Route: 744 Route Km
- Ballarshah to Kazipet – 234 Rkm
- Kazipet-Vijayawada-Gudur– 510 Rkm
- Golden Quadrilateral Route (Chennai – Mumbai section): 536 Route Km
- Renigunta to Gooty – 281 Rkm
- Gooty to Wadi – 255 Rkm
- Golden Diagonal (Grand Trunk) Route: 744 Route Km
- Already, the maximum speed limits in the High-Density Network (HDN) between Secunderabad – Kazipet (132 Kms distance) had been enhanced to 130 kmph.
- As such, including both the Up and Down lines in these sections, a total of 2,824 kms (1412 Rkms) has now been made fit to run at a speed of 130 kmph.
- This covers the entire GQ-GD route over SCR, except Vijayawada – Duvvada section, where signaling up-gradation work is in progress.
- Shri Gajanan Mallya, General Manager, SCR has specially congratulated all the Officials and staff who have put their strenuous efforts in completing all the required aspects in these sections.
- He also said that though a pandemic situation is prevailing across the globe, the staff and officers of the Zone have relentlessly worked as a team to complete the targeted work.
- He opined that the enhancement of speed in these important sections of Golden Quadrilateral/Golden Diagonal and high density routes will help in smooth operation of train services.
- He also stated that the running time of the passenger services will be considerably reduced and pave the way for running more number of trains.
Source: South Central Railway-Press Release