Nagpur Metro Update: Tender invited for shifting of electrical utilities at various metro stations for Prajapati Nagar-Transport Nagar section of Phase-2

Maharashtra Metro Rail Corporation Limited (MMRCL) has invited tender for Shifting of electrical utilities i.e. 1.1 kV LT, 11 kV HT, 33 kV HT overhead/underground lines & road crossing at 1. Pardi Metro Station, 2. Kapsi Khurd Metro Station, 3. Transport Nagar Metro Station 4. Ahead of Pardi Metro Station near substation – 33 kV HT overhead road crossing line, 5. Ahead of Pardi Metro Station near Nagpur Tiles – 11 kV HT overhead road crossing line and at any other locations as per the site conditions in Prajapati Nagar (ch.(-) 113.1 0) – Transport Nagar (ch. (-) 6021 ) section of Reach 4A of E-W corridor for NMR Phase-II project.

  • Tender No: N2-017/ELE-04/2023
  • Name of work: Shifting of electrical utilities i.e. 1.1 kV LT, 11 kV HT, 33 kV HT overhead/underground lines & road crossing at 1. Pardi Metro Station, 2. Kapsi Khurd Metro Station, 3. Transport Nagar Metro Station 4. Ahead of Pardi Metro Station near substation – 33 kV HT overhead road crossing line, 5. Ahead of Pardi Metro Station near Nagpur Tiles – 11 kV HT overhead road crossing line and at any other locations as per the site conditions in Prajapati Nagar (ch.(-) 113.1 0) – Transport Nagar (ch. (-) 6021 ) section of Reach 4A of E-W corridor for NMR Phase-II project.
  • Approximate Cost: INR 5,88,61,227/-
  • EMD: INR 2,95,000/-
  • Contract Period: 24 Months
  • Document Download Start Date: 27th July, 2023
  • Document Download End Date: 06th September, 2023
  • Pre-Bid Meeting: 10th August, 2023
  • Bid Submission Start Date: 27th July, 2023
  • Bid Submission End Date: 06th September, 2023
  • Bid Opening Date: 06th September, 2023

Scope of Work:

  • All material shall conform to relevant standards as per BIS and shall carry ISI particular category of material for which ISI mark is not available in market, It included in approved list.
  • Work shall be carried out as per the method of construction specified by BIS. if there is no reference for a particular method of construction in IS, such work shall be carried out as per the approved method of construction specified in chapter 15 of P.W. Department Handbook.
  • Material and Work not qualifying to any provision mentioned above shall be to the satisfaction of the Engineer in Charge.

Armoured cables:

  • Providing armoured cable of specified voltage level, size & specified conducting material Aluminum / Copper) including required material, hardware’s for erection and erecting on wall, ceiling, RCC slab or drawing the same through pole, pipe, laying in provided conduit, trench, ducts, trays as per approved method of construction including glands, lugs, etc.

Cables:

  • Cables shall be PVC for LT/MP and XLPE for HT and of required construction, colour, shall carry ISI mark, IS No, manufacturer’s name, size, duly embossed / screen printed at every metre and having the total count of progressive length in metre at each mark.

Saddles:

  • Saddles fabricated, from GI Sheet of required gauge and size depending on die of cable either galvanised or painted with superior quality name Black paint with necessary shearing mechanical strength, semicircular shaped with extended piece having suitable holes for fixing.
  • GI Strip: 22 x 25 mm width G I Strip.
  • Clamps: MS Clamps fabricated of required length and shape, having the size of 3/6 mm thick mild steel having 25/50 mm width (as per size of cable), rounded ends with wooden / resin cast-grip for holding the cable.
  • Identification tags: For identifying root, connection position Gl strip with identification. Mark / name embossed / painted with arrangement to tie should be fix on cable or arrangement of ferrules to be done.
  • Hardware: Sheet Metal screws of required sizes, plugs / wooden gutties, etc.

Method of Construction:

  • Irrespective of method of construction the cable ends shall be terminated with appropriate size & type of glands with lugs duly crimped, as directed by Site engineer. Wherever the cable has to be bent, the turning radius shall be as mentioned.
  • Grouping of cables shall be done with adequate distance between cables as mentioned in IS so as to minimise the jointing. Cables shall be tagged/ferruled with identification name / mark at the point from where distribution starts and at ends.
  • Bar earth wire of appropriate size As per Table- no. 1 shall run along with the cable. Earth wire running with the cable shall be terminated at the earth terminal nearest to Cable termination.

Erection of Cable on Surface:

  • Erection shall be done as per the routes and layout finalised, in perfect level and in plumb. Before fixing the cable shall be straightened as far as possible for good aesthetic look, continuous bare Gl earth wire of required gauge as per Table No 1 shall be run.
  • Cable with GI wire shall be fixed by saddles firmly clipped on cable and shall be fixed to wall, with minimum 50 x 8 mm SM screws with plugs/wooden gutties, etc. (Distance between two supports / saddles shall be maximum 450 mm).
  • Wooden gutties shall be used wherever required (especially for stone walls). The entries made in wall, floor slab, etc for laying Cable shall be made good by filling and finishing with plastering the same.

Erection of Cable on Trusses:

  • Cable along with bare Gl earth wire, while erecting on trusses, shall be firmly clamped by wrapping GI strip of 22 x 25 mm width of required length fixed to truss with nuts and bolts.

Erection of Cable on Pole:

  • Cable along with bare GI earth wire, while erecting on pole, shall be firmly clipped by suitable wooden / epoxy resin cast grips, clamped with 25 x 3 mm or 50×6 mm MS strip of required length and fixed to pole with nuts and bolts.

Laying of Cable in provided Trench/Pole:

  • While laying Cable along with bare GI Earth wire, utmost care shall be taken to prevent damage to the insulation of the cable and to the open end. Cable shall be brought out from the trench vertically straight (minimum 1 metre above G L).
  • Care shall be taken to inspect the trench so that the depth of cable shall not be less than as shown in Table No 7. Suitable size of cable loops shall be provided near the termination point at adequate depth.
  • Erecting cable in constructed Trench / duct: Erection of cables in constructed trench / duct shall be as per guidelines of IS 1255.
  • Erection of cables on trays: Cable/s shall be tied with PVC tags on Gl trays. At bending point care shall be taken so that sharp edges of sheet will not damage cable insulation of cable.
  • Mode of measurement: Executed quantity shall be measured on the basis of running metre per run of cable.

Dismantling:

  • Cable laid underground, or fixed on any surface shall be dismantled carefully without damaging complete with all its accessories, making coil and stored as directed.
  • The surface of the dismantled cable shall be made clear by removing unwanted material, cement mortar, etc. When cable is dismantled from the trench refill back the trench and make the surface proper.
  • Cable Joints & End Termination Kits Item Nos. 7.4 & 7.5 (BOQ Item sr. no. 14,16,19,22,24,26,27) (LT/HT Cables).

Outdoor/Indoor end termination Kit: LT/HT Cables:

  • Before providing an end termination kit to the cable, the cable end of the equivalent length of the moulds, shall be prepared by removing the outer PVC insulation along with the steel armoring.
  • The ferrule shall then be inserted over the bare core of the cable, and shall be crimped with a hydraulic / mechanical type heavy duty crimping tool. The crimping shall be done in such a manner that there shall be no air gap.
  • Then the crimped portion shall be wrapped first with the PVC insulation tape and then with the insulation tape used for wrapping HT conductor. The above method shall be carried out for all the cores strictly following the colour code.
  • The leads of the cable now shall be placed into the mould by using the epoxy spacer, for having sufficient gap in-between the leads.
  • The earth continuity lead shall be clamped to the intended end of the cable. After covering the cable leads with the PVC moulds, the edges shall be clipped after applying the adhesive on the inside face of the moulds.
  • The pasting of moulds shall be rigid and as far as possible leak proof, so that the epoxy compound shall not spill out Now the duly stirred epoxy compound shall be poured and filled till the compound rises through the risers provided on the moulds. (Refer drawing no. CB-JT-2).
  • After completing the above procedure, the joint shall be allowed to dry out for at least 8 to 10 hours (for epoxy compound to get hardened) depending upon the size of cable.
  • Before connecting to supply, the dry and hardened joint shall be tested for its insulation level with 1000 VI 5000 V Megger.
  • Mode of Measurement: Executed quantity will be measured on number basis, (i.e. each).

Eligibility:

  • To the exception of any equipment or any sector, which is subject to an embargo by the United Nations, the European Union or European Country, all goods and services are eligible for Maha-Metro/ ADB/ EIB financing regardless of the country of origin of the supplier, contractor, provider or sub-contractors, inputs or resources used in the implementation processes.
  • Natural or legal persons (including all members of a joint venture or any of their subcontractors) shall not be awarded an Maha-Metro/Agency-financed contract if, on the date of submission of an application or of a bid or on the date of award of a contract, they:
  • Are bankrupt or being wound up or ceasing their activities, are having their activities administered by the courts, have entered into receivership, or are in any analogous situation arising from a similar procedure;
  • Have been convicted within the past five years by court decision, which has the force of res judicata in the country where the project is implemented, of fraud or corruption or any other offence committed during the procurement or performance of a contract, unless they provide supporting information together with their Statement of Integrity (Form available as Appendix to Letter of Bid) which shows that this conviction is not relevant in the context of this Maha-Metro/Agency-financed project;
  • Are listed for financial sanctions by the United Nations, the European Union and/or European Country for the purposes of fight against terrorist financing or threat to international peace and security;
  • Have committed serious professional misconduct within the past five years during the procurement or performance of a contract, as evidenced by any means by the Employer;
  • Have not fulfilled their obligations regarding the payment of social security contributions or taxes in accordance with the legal provisions of the country where they are established or the Employer’s country;
  • Have been convicted within the past five years by court decision, which has the force of res judicata of fraud or corruption or any other offence committed in the context of an Maha-Metro/Agency-financed contract procurement or performance;
  • Are subject to an exclusion decision of the World Bank and are listed on the website, unless they provide supporting information together with their Statement of Integrity (Form available as Appendix to Letter of Bid) which shows that this exclusion is not relevant in the context of this Maha-Metro/Agency-financed project.
  • Have committed misrepresentation in documentation requested by the Employer as part of the contract procurement procedure.

About Nagpur Metro Phase-II:

  • The detailed project report (DPR) of Nagpur Metro Phase-II for extending the existing 4 corridors of Phase-I is being examined by the Prime Minister’s Office (PMO). Soon it will be put on before the Union Cabinet.
  • The 43.8 km Phase-II shall extend to Kanhan in North, Butibori MIDC in South, Transport Nagar (Kapsi) in East and Hingna in West.
  • Comprises 1.2 km at-grade with 2 stations and 42.6 km elevated with 30 stations.
  • Will connect the satellite cities like Transport Hub at Kapsi, Industrial areas of Hingna and Butibori and Mining areas at Kanhan.
  • With only one interchange at Sitabuldi Nagpur Metro Rail Project Phase-II is scheduled to be completed in 2026.
  • It consists of following 4 extensions of 2 corridors of Phase I, totaling 43.8 km:
    • MIHAN – MIDC ESR – 18.6 km
    • Automotive Square – Kanhan River – 13.0 km
    • Prajapati Nagar – Kapsi – 5.5 km
    • Lokmanya Nagar – Hingna – 6.7 km
  • Phase-II will connect the satellite cities of Nagpur and highly benefit a population of over 10 lakh residing in these areas. When it is operational, the total length of Nagpur Metro project will be 82 km.
  • The Kanhan route passes through Kamptee, which is a big town and thousands of residents commute to Nagpur for work and education purposes. They will be able to reach all corners of Nagpur fast using the Metro. Several coal mines of Western Coalfields Limited (WCL) are located near Kanhan.
  • Butibori is the biggest industrial estate in Nagpur district and thousands of Nagpurians work in the estate. There are about 750 units in Butibori, which employ around 50,000 people. The Metro will provide a fast mode of commuting to their factories.
  • Hingna is a fast developing town adjoining Nagpur. Kapsi has an industrial estate and is a transport hub.
  • The 2 phases will collectively lead to an investment of Rs 15,388 crore. There will be a substantial increase in ridership after the Phase-II of Nagpur Metro is operational.
  • The total ridership of the 2 phases after completion of Phase II is expected to be 5.5 lakh daily. This is expected to increase to 6.3 lakh in 2031 and 7.7 lakh in 2041.

Sale of document, e-payment procedure, submission and other details are available on MAHA-Metro (Nagpur) E- tender portal under section in e- tenders. https://mahametrorail.etenders.in


Source: NMRC- Tender | Image Credit (representational): Nagpur Metro

Be the first to comment

Leave a Reply

Your email address will not be published.


*