Sivok-Rangpo Project Update: Breakthrough of Tunnel No. T-03 achieves in Darjeeling, this marks overall 57% physical progress till date

In a major milestone, Tunnel no. T-03 of the Sivok – Rangpo Rail Project (SRRP), located in Darjeeling District of West Bengal, achieved a breakthrough. With this tunnel breakthrough, mining in 07 tunnels have been completed so far in this project.

More Details:

  • The length of the Main Tunnel is 1275 metres, located in between Kajijhora and Swetijhora in Darjeeling District of West Bengal. The Main Tunnel traverses through vulnerable and challenging geological and seismic conditions of the Younger Himalayas.
  • Emission of methane gas due to coal bearing formation was a big challenge during the construction of this tunnel. Regular testing for methane gas was being carried out as a safety measure to avoid any untoward incident while working.
  • Like all other tunnels in the SRRP, to counter vulnerability of the ground mass, the latest and most sophisticated tunnelling technology, i.e., New Austrian Tunneling Method or NATM has been used here.
  • An American Consultancy team has been engaged for the tunnel design in this project and the execution team includes top class and well experienced engineers & geologists from India and abroad.
  • The Sivok – Rangpo project has already achieved physical progress of 57%.This new rail link project connecting Sivok (West Bengal) and Rangpo (Sikkim) is about 45 kms long and is characterised by 14 nos. tunnels, 17 nos. bridges and 5 nos. Stations.
  • The length of the longest tunnel (T-10) is 5.3 km and length of longest bridge (Br-17) is 425 metres. About 38 kms of the entire project alignment is passing through tunnels and 83% of tunnelling work has already been completed.
  • Tunnel mining is expected to be completed by January, 2024. At present final lining has been completed in tunnel T-14 and is under progress in tunnel T-02, T-05, T-09, T-10, T-11 and T-12. Total 5.34 km lining has been completed till date and it is expected to be completed by September, 2024.
  • Work in all sections is being carried out round the clock 24×7. This is o­ne of the prestigious o­ngoing National projects in India and o­n completion of this project, first time the state of Sikkim will be connected via railways.
  • This rail network o­n its completion is aimed to provide alternate connectivity to the state of Sikkim. At present all the activities related to construction of tunnels, bridges and station yards are going o­n war footing basis to complete the project.

Source: Northeast Frontier Railway- Press Release | Image Credit (representational): MoR