Mumbai Metro Line 2A and 7 will be operational by October 2020

Share with your network

Mumbai: Metro Line 2A and 7 will be operational by October 2020, according to the reports. The Mumbai Metropolitan Region Development Authority (MMRDA) is planning to start trials on these two metro lines by August next year, it said. Around 90% of civil work has already been completed for the projects.

Metro Line-7

  • The 16.5 km long Metro Line 7 will link Andheri (East) to Dahisar (East).
  • The estimated cost of this project is Rs 6,208 crore.
  • It will provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Line 2A (Dahisar to D N Nagar) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It will facilitate smooth and efficient interchange with the suburban rail system and MRT system at Andheri, JVLR and Dahisar.
  • The metro line will provide connectivity between the Central Mumbai and the Northern suburban Mumbai.

Metro Line-2A

  • Metro Line 2A from Dahisar to D N Nagar is 18.589 km long elevated corridor with 17 stations.
  • It will provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Lines 2B (D N Nagar to Mandale) & 7 (Andheri (E) to Dahisar (E)) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It will facilitate smooth and efficient interchange with the suburban rail system and MRT system at Dahisar and D N Nagar.
  • The metro line will provide connectivity between the Western, Central Mumbai and the Northern suburban Mumbai.
  • The estimated cost of the project is Rs. 6,410 Crore.