Delhi-Ghaziabad-Meerut RRTS update: Bids invited for supply of Auxiliary Main Transformer for RRTS corridor

In continuation to the tender for for supply of traction Transformer for RRTS corridor, IRCON International Limited (IRCON) has invited online bid in Two Packet system on prescribed forms execution of the work detailed in the table given below. 

  • Tender Reference Number: NCRTC AMT1/OT/12
  • Name of Work: Design, Manufacturing & Supply of 220/33 kV, 15/20 MVA (ONAN/ONAF) Auxiliary Main Transformer including Terminal Connectors with Nitrogen Injection Fire Prevention System (NIFPS) and all accessories for the work of Delhi – Ghaziabad – Meerut RRTS Corridor of NCRTC (Package-19 Lot 1 & Lot 2).
  • Estimated Cost of Work: 4,84,51,200/-
  • Completion Period: 5 Months
  • Document Download / Sale Start Date: 16-Feb-2021 
  • Document Download / Sale End Date: 08-Mar-2021
  • Bid Submission Start Date: 03-Mar-2021
  • Bid Submission End Date: 08-Mar-2021
  • Bid Opening Date: 09-Mar-2021

Introduction of Work:

Project: Design, Supply, Installation, Testing and Commissioning of Receiving Sub Stations [including 25 kV AC Traction cum 33 kV Auxiliary Main Sub Stations], Extra High Voltage & High Voltage cabling, 25 KV Overhead Equipment (FOCS/ ROCS), Auxiliary Power Supply [including Auxiliary Sub Station], SCADA Systems, Operational Control Centre and Associated works on Viaduct & Tunnel for Delhi – Ghaziabad – Meerut RRTS Corridor of NCRTC (Lot 1 & Lot 2). 

The project is planned for a phased commissioning in 4 stages as under: 

StageSectionsTentative ROD
Stage 1Sahibabad (incl) – Duhai (EPE) including Duhai depotMarch 2023
Stage 2Duhai (EPE) – Meerut (South)December 2023
Stage 3Sarai Kale Khan – Sahibabad (excl) including Jangpura Stabling YardOctober 2024
Stage 4Meerut (South) – Modipuram including Modipuram DepotMarch 2025

Scope Of Work:

The Broad scope of work is as under:

  • Design, Manufacture & Supply of 220/33 kV, 15/20 MVA (ONAN/ONAF) Auxiliary Main Transformer including Terminal Connectors with Nitrogen Injection Fire Prevention System (NIFPS) and all accessories mentioned in the brief Particular Specifications enclosed at Annexure-A with complete packing, loading, transporting to the work Site at Muradnagar RSS and Sahibabad/Ghaziabad RSS. All the Equipment and accessories offered shall be in full Technical conformity with the brief Particular Specifications enclosed at Annexure-A.
  • Factory Inspection of all Material before dispatch.
  • Supervision at site during Installation, Testing & Commissioning.
  • Training to authorized personnel of NCRTC. 

Delivery Period/ Milestone Target: 

The Contractor shall be required to supply the equipment/material as per the schedule given below:

S. NoStage & LotSubstationDelivery Date/ Milestone Target
1Stage-1, Lot-1Sahibabad/Ghaziabad RSS5 Months from issue of LOA
2Stage-2, Lot-2Murad Nagar RSS5 Months from issue of LOA

Website https://etenders.gov.in/eprocure/app may be referred for detailed terms and conditions of the bidding documents, which is available on line.


Source: IRCON-Tender | Image Credit: NCRTC